Problems And Obstacles Which Constrain the Optimal Construction Site Management into Libyan Large-Scale Projects
Abstract
The management of the construction site (CSM) includes a combination of a number of activities that can reflect the project in its final form and directly influence security, material supply, resource utilisation, health and safety, planning, cost, and all other aspects of construction that permeate the implementation of the project. Practically, it is not a simple procedure to manage a site successfully. Construction work has become a complex set of processes, and there are numerous management challenges that are continually occurring on construction sites. Hence the importance of this paper, which aims to study "problems and obstacles that constrain the optimal management of the construction site, as well as to identify approaches and methods that can be used to address these difficulties and obstacles and solve these problems." This study adopted a mixed approach that included many research activities, including an in-depth review of the relevant literature to explore the most important problems facing CSM and the possible solutions used in previous studies. In the context of the on-site study, a qualitative approach, including field visits and semi-structured interviews, was used within five large-scale projects suggested by organizations that have worked on behalf of GMRWUA in Libya. This was followed by an assessment of the CSM Problems in terms of their importance and frequency of occurrence through the use of the quantitative approach (questionnaire).The main findings of the paper focus on the identification and classification of the problems of the CSM in terms of their effect on managing construction sites, and their frequency of occurrence. In addition, the problem-solving approaches to be taken by the CSM team were identified in the GMRWUA Projects, which can help in mitigating the CSM problems in future.
Full text article
References
[1]-T. Holroyd, Site Management for Engineers. London: Thomas Telford, 1999.
[2]-Hassan, P. F., Griffith, A., Stephenson, P., (2005), An empirical study of the training needs of site managers within the UK construction industry, Association of Researchers in Construction Management, 1, 95-104.
[3]-M. ALI, A Framework for Enhancing the Success of Construction Projects Undertaken In Libya. doctoral diss, Sheffield Hallam University, the UK 2011[4]-CIRIA, Faster Construction on Site by Selection of Methods and Material. CIRIA Report C560. London,2001.
[5]-5H. Robinson, P. Carrillo, C. Anumba, A. Al-Ghassani, Knowledge management: towards an integrated strategy for construction project organizations, (Unpublished work).
[6]-Wideman, R. M., (1986), The PMBOK report: PMI Body of Knowledge Standard. Project Management Journal, 17(3), 15-24.
[7]-R. Newcombe, D. Langford, R. Fellows, Construction Management: Organisation Systems. London: B. T. Batsford, 1993.
[8]-J. Fapohunda, Operational Framework for Optimal Utilisation of Construction Resources during the Production Process, doctoral diss, Sheffield Hallam University, the UK 2009.
[9]-A. Al Zoghbi, Project Management –Causes Of Delay In Libyan Construction Industry, Master Diss, Middlesbrough, The UK 2011.
[10]-M. Alzohbi, P. Stephenson, A. Griffith, (2011), An Investigation of Problematic Issues Associated with Construction Site Management. ARCOM: Association of Research in Construction Management, 28(2), 12-23.
[11]-Anumba, C J., Mohamed, S F., (2006) Potential for improving site management practices through knowledge management. Construction Innovation Journal, 6, 232-246.
[12]-Harlow, P. A., (1985), The Practice of Site Management. The Chartered Institute of Building, 3, 7-9.
[13]-R. Fellows, D. Langford, R. Newcombe, S. Urry, Construction Management in Practice. (2nd ed). Oxford: Blackwell Science Ltd, 2002.
[14]-Construction I.T, enchmarking best practices construction site processes; Construct I.T., 9116.
[15]-J. Illingworth, Construction Methods and Planning, (2nd ed). London: E&F Spon, 2000.[16]-Mohamed, S. F., Anumba, C. J., (2004), Towards a framework forintegrating knowledge management processes into site management practices, ARCOM, 1(3), 45–54.
[17]-M. Alzohbi, An Investigation of Problematic Issues Associated with Site Management –The Case Study of Great Man-made River Projects in Libya, Master diss, Sheffield Hallam University, the UK 2008.
[18]-K. DeCuyper, Site Organisation and Management. In: ENBRI (ed.) R&D for the Construction Site Process, 1993.
[19]-J. Wild, Site Management of Building Services Contractors. Oxford: E&FN Spon, 1997.
[20]-Li, H., Love, P., (2000).,Genetic search for solving construction site-level unequal-area facility layout problems. Automation in Construction, 9(2), 217-226.
[21]-Toor, S. R., Ogunlana, S., O., (2008), Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4), 395-408.
[22]-M. Abadi, Issues and Challenges in Communication within Design Teams in the Construction Industry, doctoral diss, University of Manchester, the UK 2005.
[23]-R. Spilsbury, R, At the Building Site: Technology at Work, Capstone Global Library, 2008.
[24]-P. Barton, The Co-ordination of Mechanical and Electrical Services Sub-contractors within the Building Process: University of Salford, 1976.
[25]-D. Doran, Quality Management. In: D. Doran (ed.) Site Engineer Manual. Chapter1, Glasgow: Whittles Publishing, 2004.
[26]-A. Kimmance, An Integrated Product and Process Information Modelling System for On-Site Construction, doctoral diss, Loughborough University, the UK 2002.
[27]-A. Morrison, D. Morrison, Looking around: Pupils book. Heinemann, 1993.
[28]-Mustapha, F., Naoum, S., (1998), Factors influencing the effectiveness of construction site managers. International Journal of Project Management, 16(1), 1-8.
[29]-Ibn-Homaid, N. T., (2002), A comparative evaluation of construction and manufacturing materials management. International Journal of Project Management, 20(1), 263-270.
[30]-P. Guthrie, C. Woolveridge, S. Coventry, S. Wilson, Managing material and components on site. London: CIRIA, 1998.
[31]-A. Griffith, P. Watson, Construction Management: Principles and Practice. Basingstoke: Palgave Macmillan, 2004.
[32]-Cheng, E. W., Li H., (2004), Construction safety management: an exploratory study from China. Construction Innovation, 4, 229-241.
[33]-Burgess, R., and Enshassi, A., (1990), Training for Construction Site Managers Involved with Multicultural Work Teams. Project Management, 8(2), 95-101.
[34]-Love, P., Holt, G., Li, H., (2002), Triangulation in construction management research. Engineering Construction and Architectural Management; 9, 294-303.
[35]-R. Fellows, A. Liu, ResearchMethods for Construction. Oxford: Blackwell, 2008.
[36]-J. Creswell, Research design: Qualitative, Quantitative and Mixed Methods Approaches. 4th ed., London, Sage Publications, (2013)
[37]-N. Binti-Kasim, Improving Materials Management on Construction Projects, doctoral diss, Loughborough University, the UK 2008.
[38]-M. Alzohbi, A Framework for Evaluating Materials Management Performance in Jordanian Concrete Building Projects, doctoral diss, Sheffield Hallam University, the UK 2015.
[39]-D. Loucks, The Great Man-Made River in Libya: Does it make Sense? The Third Annual D. R. F. Harleman Honorary Lecture in Environmental Fluid Mechanics, the Pennsylvania State University, Pennsylvania. 2004.
[40]-Bresnen, M., Bryman, A., Beardsworth, T., (1987), Effective Construction Site Management. In: P. Harlow (ed.) Technical Information Service. 85, 1-6. Berkshire: The Chartered Institute of Building (CIOB).
[41]-Anbari, F. T., Khilkhanova, E. V., Romanova, M. V., Ruggia, M., Tsay, H.-H., & Umpleby, S. A. (2009). Managing cross cultural differences in projects. Paper presented at Project Management Institute (PMI).
[42]-Luong, H., Tsunemi W., (2017), The Impact of Project Organizational Culture on the Performance of Construction Projects, Sustainability, 9, 1-21, 781.
[43]-S. Coakes, C. Ong, SPSS Version 18.0for Windows: Analysis without Anguish. Milton: John Wiley, 2010.
[44]-A. Field, Discovering Statistics Using SPSS: and sex and drugs and rock 'n' roll. (3rd ed.), London: Sage, 2009.
[45]-Wang, S. Q., Tiong, R. L. K, Ting, S. K., Ashley, D., (1999). Risk Management Framework for BOT Power Projects in China. Journal of Project Finance, 4(4), 56-67.
[46]-Akintoye, A., Mcintosh, G. And Fitzgerald, E., (2000), A Survey of Supply Chain Collaboration and Management in the UK Construction Industry. European Journal of Purchasing & Supply Management, 6, 159-168.
[47]-R. Takim, Framework for Successful Construction Project Performance. Doctoral diss, Glasgow Caledonian University, the UK 2005.
[48]-J. Hatmoko, The Impact of Supply Chain Management Practice on Construction Project Performance. Doctoral diss, Newcastle University, the UK 2008. [
9]-11B. LI, Risk Management of Construction Public Private Partnership Projects. doctoral diss, Glasgow Caledonian University, 2003.
[50]-A. Higham, Conceptual Framework for the Sustainability Benefit Evaluation of UK Social Housing Projects, doctoral diss, Sheffield Hallam University, the UK 2014.
[51]-Bryman, A. (2008). Social Research Methods. 3rd ed., Oxford, Oxford University Press.
[52]-Boyer, K. K. And Swink, M. L. (2008). Empirical Elephants-why Multiple Methods are Essential to Quality Research in Operations and Supply Chain Management. Journal of Operations Management, 26(3), 337–348.
[53]-Singhal, V., et al., (2008), Editorial: Empirical Elephants-Why Multiple Methods are Essential to Quality Research in Operations and Supply Chain Management. Journal of Operations Management, 26, 337-348.
[54]-Tangpong, C., (2011), Content Analytic Approach to Measuring Constructs in Operations and Supply Chain Management. Journal of Operations Management, 29, 627–638.
[55]-E. Babbie, The Practice of Social Research, (7th ed.), Harrisonburg, VA, Wadsworth Publishing, 1995
Authors

This work is licensed under a Creative Commons Attribution 4.0 International License.
In a brief statement, the rights relate to the publication and distribution of research published in the journal of the University of Sebha where authors who have published their articles in the journal of the university of Sebha should how they can use or distribute their articles. They reserve all their rights to the published works, such as (but not limited to) the following rights:
- Copyright and other property rights related to the article, such as patent rights.
- Research published in the journal of the University of Sebha and used in its future works, including lectures and books, the right to reproduce articles for their own purposes, and the right to self-archive their articles.
- The right to enter a separate article, or for a non-exclusive distribution of their article with an acknowledgment of its initial publication in the journal of Sebha University.
Privacy Statement The names and e-mail addresses entered on the Sabha University Journal site will be used for the aforementioned purposes only and for which they were used.